DETAIL ENGINEERING REQUIREMENTS Section 9, ATT-TP-76400
AT&T January, 2012
In those locations where space is limited and any of the new FDFs will not fit or cannot be
installed then at the request of the MEI/IE with the use of a JIM an older style bay may be
installed without the need for a waiver.
6.4.14 Under no condition, unless for testing or trouble shooting purposes, shall fibers be left
UNTERMINATED at any Fiber Optic Termination Panel (FTP). Examples of FTP’s would
include but may not be limited to FDF’s, LGX’s FDP’s, FIP’s or Fiber Drawers.
Any temporary test patch or loop back setup for testing or trouble shooting purposes shall not
be left up more than 24 hours unless concurred by the GNFO. Any loopbacks, which are
placed on the LGX at each end terminal site until integration testing can perform at either end
and cleared with the GNFO, is permitted. In these cases, a tag must be applied with the OTV
name, order number and date applied.
And, all fibers removed (unterminated) for testing or trouble shooting purposes shall have
dust caps placed over the end of the fiber as well as any vacated jack/port position a dust cap
shall be placed on that jack/port position.
Any fibers which are left as spares and are bagged and tagged and are required by the Telco
order to be left on site are also permitted.
9-17